Project Description
This project includes the design and construction of a new pedestrian sidewalk on Melbourne Street from US 41 to Harborview Road.Project Location
Melbourne Street from US 41 to Harborview Road in Charlotte Harbor.Project Impacts
Due to Hurricane Ian, the scheduled has been delayed.Latest Updates
Johnson Engineering has submitted the 60% design plans to Charlotte County. County staff has reviewed and provided comments back to Johnson Engineering.
Charlotte County BOCC has provided guidence to staff at the May 21st meeting to proceed with the design of the sidewalk along Melbourne.
Budget
Phase | Cost |
---|---|
Design | $182,080 |
Construction | $686,000 |
Total Budget | $868,080 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 01/10/2022 | 07/11/2022 | 07/08/2022 |
Design Development | 07/12/2022 | 06/24/2024 | |
Construction | 10/05/2024 | 12/30/2024 | |
Turnover & Closeout | 12/30/2024 | 01/31/2025 |
Project Phase
Design Development
Last Updated
05/27/2024
Project Manager
Jeff Keyser
Public Relations
Tracy Doherty
Email Public Relations
Project Number
c192205
Sponsor Department
Public Works
Design Engineer/Architect
Johnson Engineering
Construction Contractor
TBD